FAS Research Computing - Cannon cluster degraded – Incident details
All systems operational
Status page for the Harvard FAS Research Computing cluster and other resources.
WINTER BREAK: Harvard and FASRC will be closed for winter break as of Sat. Dec 21st, 2024. We will
return on Jan. 2nd, 2025. We will monitor for critical issues. All other work will be deferred until we return.
Cluster Utilization (VPN and FASRC login required): Cannon | FASSE
Please scroll down to see details on any Incidents or maintenance notices.
Monthly maintenance occurs on the first Monday of the month (except holidays).
The colors shown in the bars below were chosen to increase visibility for color-blind visitors. For higher contrast, switch to light mode at the bottom of this page if the background is dark and colors are muted.
Cannon cluster degraded
Resolved
Degraded performance
Started 4 months agoLasted about 5 hours
Affected
Cannon Cluster
SLURM Scheduler - Cannon
Cannon Compute Cluster (Holyoke)
Boston Compute Nodes
GPU nodes (Holyoke)
seas_compute
Updates
Resolved
Resolved
The power issue has been resolved. All nodes that were drained are now being re-opened.
Investigating
Investigating
Due to temporary power availability issues in MGHPCC, half the nodes in 8A have been set to drain. This affects all partitions. Jobs will take longer to schedule but will not be terminated.
We will reopen these nodes once the power issue has been resolved at the datacenter. No ETA at this time